Project Overview: Powering Commercial Offices with a 45kVA Three-Phase Generator
In June 2024, Target Power successfully delivered a tailored power solution to Northeast Dealer, a business needing consistent and reliable electricity for a commercial office complex. The project centered around the TY45 Yanmar-powered 45kVA prime generator, built with a 200 amp Automatic Transfer Switch (ATS), to ensure seamless power transfer and eliminate downtime during grid outages.
The generator is powered by a Yanmar 4TNV98T-GGEA diesel engine, paired with a Stamford alternator and a DSE 6120 control panel. This robust combination is housed in a soundproof generator canopy designed to ensure proper airflow and temperature regulation.
Application: Reliable Power for Office Operations
The generator was required to power the electrical systems of the office complex, a critical need to support lighting, computers, air conditioning, and other essential office functions. The 45kVA prime / 49.5kVA standby generator was selected for its reliability and efficiency in commercial settings. This three-phase unit is capable of handling significant loads and ensuring uninterrupted power supply to the office.
Overcoming Challenges: Custom Silent Canopy Design for Airflow
One of the main challenges faced was the need for a compact design that could still deliver the necessary power output. Our engineering team custom-designed the canopy to fit the CKD arrangement while allowing for sufficient airflow. This modification ensures that the generator operates efficiently without overheating, even in continuous operation.
Product Selection: Reliability and Peace of Mind
The Yanmar 4TNV98T-GGEA engine was specifically chosen for its industry-leading reliability, backed by a 5-year standby warranty. This long-term warranty provides the customer with confidence in the longevity and performance of the generator, crucial for minimizing operational disruptions in their office environment.
Services Provided: Comprehensive Power Solution
Target Power managed the entire process from design and assembly to delivery. The 200 amp ATS, equipped with a Terasaki contactor, ensures smooth transition during power outages, protecting sensitive office equipment. Delivery to the site was carried out using a Target Power vehicle, ensuring safe and timely arrival.
Project Completion: Delivered on Time and On Budget
From the initial inquiry to delivery, the project took a total of 6 weeks, including 4 weeks of assembly. Despite the need for a customized design, Target Power delivered the solution on time and within budget, exceeding the client’s expectations for a reliable commercial power source.